February Update

During the last quarter of 2015, the Remedial Design team continued to collect field data and to submit reports to EPA presenting the findings from the various design investigations. The ongoing field work […]

February 15th, 2016|

August Update

The Design Team and its contractors remain engaged in several activities on or near the canal.

Drilling for Bulkhead Study

In August, the field team will conclude the first phase of canal bulkhead assessments. This work included soil sample collection, geophysical tests and boring […]

August 31st, 2015|Tags: |

July Update

The Design Team and its contractors continue working on several projects on the canal.

Drilling for Bulkhead Study: As part of EPA’s remedy, dredging will be required along existing bulkheads. Through the bulkhead study, we […]

July 28th, 2015|

June Update

The Design Team and its contractors remain engaged in several activities on the canal as the warm summer weather continues.

Drilling for Bulkhead Study: As part of our continuing study of bulkheads in the […]

June 16th, 2015|

May Update

As the spring weather continues, the Design Team and its contractors remain engaged in several activities on the canal.

Upcoming Work

Groundwater Studies: We will collect data to better characterize how groundwater enters the Canal. […]

March Update

The Design Team and its contractors are currently engaged in several activities on the canal. These activities are part of their ongoing effort to further study the canal and develop the remedial design. Information gained from these studies will help the Environmental Protection Agency (EPA) and the Design Team […]