September 2015

September Update

September 22nd, 2015|

Over the past few weeks, the Design Team and its contractors continued efforts on three areas of study which began earlier this year. These three on-going projects are:

  • Groundwater Studies: This month we continue with the data collection discussed in our May update. For more […]

May 2015

May Update

May 26th, 2015|

As the spring weather continues, the Design Team and its contractors remain engaged in several activities on the canal.

Upcoming Work

Groundwater Studies: We will collect data to better characterize how groundwater enters the Canal. […]

April 2015

April Update

April 28th, 2015|

As the spring weather continues, the Design Team and its contractors remain engaged in several activities on the canal.

Upcoming Work

Sediment Studies: We will collect sediment throughout the canal for testing. These samples will guide […]

January 2015

January Update

January 21st, 2015|

The Design Team and its contractors are currently engaged in several activities on the canal. These activities are part of our ongoing effort to further study the canal and develop the remedial design. Information gained from these studies will help the Environmental Protection Agency (EPA) and the Design Team […]