Progress Update, Week of July 26, 2021
During the week of July 26 the Gowanus Remediation Team completed repositioning the work barges around the Carroll Street bridge.
During the week of July 26 the Gowanus Remediation Team completed repositioning the work barges around the Carroll Street bridge.
Dredged material is processed according to the Level 1 Archaeological Monitoring protocol outlined in the draft Cultural Resource Monitoring Plan (revised September 2020).
During the week of July 19 the Gowanus Remediation Team continued repositioning the work barges around the Carroll Street bridge.
During the week of June 14 the Gowanus Remediation Team continued with ongoing pile driving operations.
During the week of July 12 the Gowanus Remediation Team continued repositioning the work barges around the Carroll Street bridge.
This memorandum presents the findings of the Archeologist’s review of screened sediments at the dredge material processing facility in New Jersey from Level 1 Monitoring.
During the week of July 5 the Gowanus Remediation Team continued repositioning the work barges around the Carroll Street bridge.