During the week of July 4, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) near the Union Street Bridge. Daily closures were in effect during work between bridge abutments. Please visit https://gowanussuperfund.com/bridge-information/ for more information about extended bridge closures.
A staging platform at the Union Street Bridge was disassembled in preparation for upcoming submarine cable installation.
Monopile installation was completed at the 3rd Street Bridge.
Anchor points installation was completed in preparation for upcoming hase 3 dredging.
Photos of construction activities are provided below.