During the week of July 11, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) south of the Union Street Bridge.
A trench for the permanent submarine cables at the Union Street Bridge was excavated within the canal.
Anchor blocks were placed in preparation for upcoming Phase 3 dredging.
Photos of construction activities are provided below.