Skip to content

Progress Update, Week of September 5th, 2022

During the week of September 5, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging between 3rd Street and Carroll Street.

The secondary ISS platform was fully demobilized.

Staging platforms were reinstalled and control cables were installed at the Union Street Bridge.

Samples were collected and analyzed at the eastern Union Street Bridge pier.

Sediment was removed, sealant was placed, and sheet piles were cut to the correct height near the Carroll Street Bridge.

Photos of construction activities are provided below.

Phase 3 Dredging in progress.
Pulling cables at the Union Street Bridge.
Transporting dewatered sediment to dredge material processing facility.