During the week of June 17, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
Supplemental dredging near Douglass Street continued. Sediment was removed. Controlled Low Strength Material (CLSM) was placed.
Probing activities were conducted at bulkheads near 3rd Street in RTA 2.
Photos of construction activities are provided below.