During the week of December 9, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System operations.
Bulkhead installation continued at the 4th Street Turning Basin. Tieback installation continued. Grout was placed. Quality assurance testing was performed.
Bulkhead installation was completed at the 7th Street Turning Basin. The site was demobilized.
Bulkhead installation began near 9th Street. Obstructions were removed. Sheet pile installation began.
Photos of construction activities are provided below.