Progress Update, Week of April 28th, 2025

During the week of April 28, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.

Bulkhead installation continued at the 4th Street Turning Basin. Grout was placed. Site restoration was performed at completed bulkheads.

Bulkhead installation continued near 3rd Street. Grout was placed.

Bulkhead installation continued at the 7th Street Turning Basin. Tiebacks were installed.

Bulkhead installation continued near Bush Street. Sheet piles installation continued.

Photos of construction activities are provided below.

Sheet pile installation near Bush Street.
Tieback installation in progress at the 7th Street Turning Basin.