Progress Update, Week of February 9th, 2026

During the week of February 9, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.

Bulkhead installation continued at the 6th Street Turning Basin. Tiebacks were installed. Grout was placed.

Bulkhead installation continued at the 7th Street Turning Basin. Underpinning of upland structures continued. Sheet piles were cut to grade.

Bulkhead installation continued near 9th Street. Preparations were made for upcoming formwork.

Photos of construction activities are provided below.

Sheet pile cutting at the 6th Street Turning Basin.
Formwork preparations near 9th Street Turning Basin.