Progress Update, Week of April 20th, 2026

During the week of April 20, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.

Bulkhead installation continued near Bond Street. Tiebacks were installed.

Bulkhead installation continued at the 7th Street Turning Basin. Tiebacks were installed.

Bulkhead installation continued near 3rd Street. Tiebacks were installed.

Bulkhead installation continued near 9th Street. A cap plate was installed.

Photos of construction activities are provided below.

Sheet piles preparing for tieback installation at the 7th Street Turning Basin.
Installing a cap plate near 9th Street.