Progress Update, Week of April 10th, 2023

During the week of April 10, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material placement continued and results were surveyed.

This week the GRT began installing a specialized cap and ventilation system at the Carroll Street Bridge. Divers and equipment were mobilized. Sediment was graded in preparation for vent pipe installation.

Photos of construction activities are provided below.’

Capping material placement in progress.
Divers mobilizing at the Carroll Street Bridge.