Skip to content

Progress Update, Week of April 15th, 2024

During the week of April 15, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.

Monopiles were cut to an appropriate height at the Carroll Street Bridge and at the Union Street Bridge. Monopiles were capped and fender installation began at the Third Street, Carroll Street, and Union Street Bridges.

Stone and concrete placement was completed.

Preparations were made for upcoming survey work.

Photos of construction activities are provided below.

 Carroll Street Bridge monopile.
Fender installed at the Third Street Bridge.