During the week of April 18 the Gowanus Remediation Team (GRT) continued Phase 2 dredging near the Union Street Bridge. Please note that the Union Street Bridge may be closed between 9am and 2pm on days when dredging is in progress at the bridge. Visit the GowanusSuperfund.com homepage for the latest bridge status updates.
At Degraw Street workers continued cutting drainage holes, installing a filtration system, and restoring the roadway. A partial street closure will remain in place on Degraw Street between Bond Street and the Gowanus Canal while this work is ongoing.
The employee parking space was reorganized at the Huntington Street staging area.
Photos of construction activities are provided below.