Progress Update, Week of August 12th, 2024

During the week of August 12, the Gowanus Remediation Team (GRT) completed the RTA 1 Capping Operation. Supplemental dredging was completed. Monopile fenders were installed. Anchor points were removed. The main channel remediation for RTA 1 is now complete!

RTA 2 Access Dredging continued in preparation for upcoming bulkhead installation. Access dredging was performed within Turning Basin 7 (TB7). Additional bulkhead monitoring equipment was installed.

Photos of construction activities are provided below.

Access Dredging in progress at TB7.
Continued Access Dredging in progress at TB7.