Progress Update, Week of August 15th, 2022

During the week of August 18, the Gowanus Remediation Team (GRT) completed mobilization and commenced with Phase 3 Dredging began between 3rd Street and Carroll Street.

The primary ISS platform was fully demobilized.

Installation of support brackets and additional supports continued for the permanent submarine cables at the Union Street Bridge. A trench for the cables was excavated. Divers were mobilized in anticipation of upcoming work.

Sediment removal continued at the Union Street Bridge piers. Sediment and debris were hand excavated with a water jet.

Photos of construction activities are provided below.

Beginning Phase 3 Dredging.
Transloading sediment at the staging area.
Excavating cable trench at Union Street Bridge.
Installing cable conduit at Union Street.