Progress Update, Week of August 19th, 2024

During the week of August 19, the Gowanus Remediation Team (GRT) continued the RTA 2 Access Dredging Operation.

Access dredging was performed within Turning Basin 7 (TB7) and near 9th Street. Additional bulkhead monitoring equipment installation continued.

Photos of construction activities are provided below.

Access Dredging in progress at TB7.
Continued Access Dredging in progress near 9th Street.