During the week of August 29, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging between 3rd Street and Carroll Street.

The secondary ISS platform was kept on standby and began demobilization as ISS sample result analysis was completed.

Divers completed placing concrete blocks and sealant at the submarine cable trench at the Union Street Bridge.

Samples were collected and analyzed at the Union Street Bridge pier.

Timber mats were removed and the street was cleaned at the DeGraw Street End sheet pile installation site.

Photos of construction activities are provided below.

Phase 3 Dredging in progress.
Continued Phase 3 Dredging.
Transloading sediment at the staging area.