Progress Update, Week of August 4th, 2025

During the week of August 4, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.

Bulkhead installation continued near 9th Street. Grout was placed.

Bulkhead installation continued at the 6th Street Turning Basin. Backfilling continued. Tiebacks were installed. Grout was placed.

Bulkhead installation continued near 3rd Street. Tiebacks were installed. Grout was placed. Piles were driven.

Photos of construction activities are provided below.

Pile installation at the 6th Street Turning Basin.
Tieback installation near 3rd Street.