During the week of August 5, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Gravel placement near Douglass Street continued.

RTA 2 Access Dredging continued in preparation for upcoming bulkhead installation. Access dredging was performed within Turning Basin 7 (TB7).