Progress Update, Week of August 7th, 2023

During the week of August 7, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed between Carroll Street and 3rd Street. Additional material was placed manually between Union Street and Carroll Street and.

Photos of construction activities are provided below.

Capping material placement in progress between Carroll Street and Third Street.
Manual material placement in progress between Union Street and Carroll Street.