Progress Update, Week of August 8th, 2022

During the week of August 8, the Gowanus Remediation Team (GRT) completed In Situ Stabilization (ISS) in Remediation Target Area 1 (RTA 1). The primary ISS platform began demobilization.

Dredge platforms and hopper barge were mobilized and anchor blocks were placed in preparation for Phase 3 Dredging.

Installation of support brackets and additional supports continued for the permanent submarine cables at the Union Street Bridge.

Sediment removal continued at the Union Street Bridge piers. Sediment and debris were hand excavated with a water jet.

Photos of construction activities are provided below.

ISS in progress.
Sediment removal at the Union Street Bridge pier.