Progress Update, Week of December 16th, 2024

During the week of December 16, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System operations.

Bulkhead installation continued at the 4th Street Turning Basin. Tieback installation continued. Grout was placed. Quality assurance testing was performed.

Bulkhead installation continued at the 7th Street Turning Basin. Gravel was backfilled.

Bulkhead installation began near 9th Street. Sheet pile installation continued. Gravel was backfilled.

Photos of construction activities are provided below.

Sheet pile installation in progress near 9th Street.
Backfilling in progress near 9th Street.