During the week of December 29, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.
Bulkhead installation continued near 9th Street. Excavation was conducted. Controlled Low-Strength Material (CLSM) was placed.
Bulkhead installation continued near 3rd Street. Tiebacks were installed.
Bulkhead installation continued at the 6th Street Turning Basin. Tiebacks were installed.
Bulkhead installation continued at the 7th Street Turning Basin. Underpinning of upland structures continued.
Photos of construction activities are provided below.