Progress Update, Week of December 30th, 2024

During the week of December 30, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System operations.

Bulkhead installation continued at the 4th Street Turning Basin. Tieback installation continued. Grout was placed. Quality assurance testing was performed.

Bulkhead installation continued at the 7th Street Turning Basin. Preparations were made for tieback installation.

Bulkhead installation began near 9th Street. A partially collapsed historic bulkhead was demolished. Sheet pile installation continued.

Photos of construction activities are provided below.

Tie back installation in progress near the 4th Street Turning Basin.
Historic bulkhead demolition near 9th Street.