During the week of December 4, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
Armor layer placement continued this week. Mattresses were delivered and placed along the bed of the canal north of Union Street.
Photos of construction activities are provided below.
![](https://gowanussuperfund.com/wp-content/uploads/2024/01/Picture9.png)
![](https://gowanussuperfund.com/wp-content/uploads/2024/01/Picture10.png)