During the week of December 5, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging north of Union Street. Surveying was conducted to review dredging results.
Demobilization of the temporary cable system was completed at the Union Street Bridge. Additional steel grating platforms placement began.
Mobilization continued at the new GRT staging area. Demobilization continued at the current GRT staging area.
Photos of construction activities are provided below.