Progress Update, Week of February 14th, 2022

During the week of February 14 the Gowanus Remediation Team continued In-Situ Stabilization (ISS) north of the Carroll Street Bridge. Additional probing of the sediment was conducted in the vicinity to identify possible obstructions.

At Degraw Street the GRT continued mobilizing equipment and preparing the site for tieback installation. A closure sheet was installed at the bulkhead. Please note, there will be a partial street closure in place on Degraw street between Bond Street and the Gowanus Canal while this work is ongoing.

At Turning Basin 1 (TB1) tieback installation continued. Tie rods were tightened. An excavator was demobilized from the site.

Photos of construction activities are provided below.

Photo of tiebacks at TB1 pipe pile bulkhead.
Installation of ISS columns.
Continued installation of ISS columns.
Stone being spread at TB1.
Tieback equipment and materials staged at Degraw Street.
Tieback installation in progress at Degraw Street bulkhead.