During the week of February 21 the Gowanus Remediation Team continued In-Situ Stabilization (ISS) south of the Union Street Bridge. Additional probing of the sediment was conducted near the Carroll Street Bridge to identify possible obstructions.
Tieback installation was completed at Turning Basin 1 (TB1). The fence and gate at the edge of the site were replaced. Equipment and materials were fully demobilized.
Tieback installation began at Degraw Street. Additional equipment was delivered to the site. There will be a partial street closure in place on Degraw street between Bond Street and the Gowanus Canal while this work is ongoing.
Photos of construction activities are provided below.