Progress Update, Week of February 23rd, 2026

During the week of February 23, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.

Crews conducted snow removal at all active work zones.

Bulkhead installation continued at the 6th Street Turning Basin. Tiebacks were installed. Grout was placed.

Bulkhead installation continued at the 7th Street Turning Basin. Sheet piles were installed. Installed sheets were backfilled.

Bulkhead installation continued near Bush Street. Obstructions were removed. Sheet piles were installed.

Photos of construction activities are provided below.

Snow removal in progress.
Obstruction removal near Bush St.