During the week of February 28 the Gowanus Remediation Team continued In-Situ Stabilization (ISS) south of the Union Street Bridge.
At Degraw Street the GRT continued tieback installation. There will be a partial street closure in place on Degraw Street between Bond Street and the Gowanus Canal while this work is ongoing.
At Turning Basin 1 (TB1) tieback installation continued. Drainage holes were cut in the temporary separation wall and tie rods were installed and tightened. Test pitting was conducted as part of the archeological monitoring program.
Photos of construction activities are provided below.