During the week of February 3, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System operations.
Bulkhead installation continued at the 4th Street Turning Basin. Tieback installation continued. Site restoration was performed at completed bulkheads.
Bulkhead installation continued at the 7th Street Turning Basin. Obstructions were removed. Sheet pile installation continued.
Bulkhead installation began near 9th Street. Tieback installation continued.
Photos of construction activities are provided below.