During the week of February 6, the Gowanus Remediation Team (GRT) continued the Demonstration Test for the RTA 1 Capping Operation.
A cable terminal box was replaced at the Union Street Bridge.
Mobilization continued at the new GRT staging area.
Photos of construction activities are provided below.