Progress Update, Week of January 10th, 2022

During the week of January 10, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.

Sealing the sheet pile bulkheads at the headwall of the canal was completed. The work barges are preparing to relocate south to Degraw Street where they will continue sheet pile bulkhead installation.

Site clearing was completed at the former Turning Basin 1 (TB1). Sheet pile installation is expected to begin at TB1 over the coming weeks.

This week crews continued removing the sound curtain fence near Union Street.

Photos of construction activities are provided below.

Grading and moving material within TB1.
Continued removal of sound curtain.
ISS in progress.