Progress Update, Week of January 19th, 2026

During the week of January 19, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.

Bulkhead installation continued near Bush Street. Installed sheet piles were cut to grade.

Bulkhead installation continued at the 6th Street Turning Basin. Tiebacks were installed. Grout was placed.

Bulkhead installation continued at the 7th Street Turning Basin. Underpinning of upland structures continued.

Bulkhead installation continued near 9th Street. Preparations were made for upcoming formwork.

Photos of construction activities are provided below.

Tieback installation at the 6th Street Turning Basin.
Underpinning at the 7th Street Turning Basin.