Progress Update, Week of January 26th, 2026

During the week of January 26, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.

Bulkhead installation continued at the 6th Street Turning Basin. Tiebacks were installed. Grout was placed.

Bulkhead installation continued at the 7th Street Turning Basin. Underpinning of upland structures continued.

Bulkhead installation continued near 9th Street. Preparations were made for upcoming formwork.

Photos of construction activities are provided below.

Underpinning at the 7th Street Turning Basin.
Continued underpinning at the 7th Street Turning Basin.