Progress Update, Week of January 27th, 2025

During the week of January 27, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System operations.

Bulkhead installation continued at the 4th Street Turning Basin. Tieback installation continued.

Bulkhead installation continued at the 7th Street Turning Basin. Obstructions were removed. Sheet piles were installed. Tieback installation continued.

Bulkhead installation began near 9th Street. Sheet pile installation continued. Installed sheet piles were backfilled.

Photos of construction activities are provided below.

Obstruction removal at the 7th Street Turning Basin
Sheet pile installation near 9th Street.