During the week of January 30, the Gowanus Remediation Team (GRT) continued the Demonstration Test for the RTA 1 Capping Operation.
Sealant placement was completed near the Union Street Bridge.
Mobilization continued at the new GRT staging area.
Photos of construction activities are provided below.