During the week of January 5, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.
Bulkhead installation continued near Bush Street. Installed sheet piles were cut to grade.
Bulkhead installation continued at the 6th Street Turning Basin. Tiebacks were installed.
Bulkhead installation continued at the 7th Street Turning Basin. Underpinning of upland structures continued.
Bulkhead installation continued near 9th Street. Tiebacks were installed. Grout was placed.
Photos of construction activities are provided below.