Progress Update, Week of January 6th, 2025

During the week of January 6, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System operations.

Bulkhead installation continued at the 4th Street Turning Basin. Tieback installation continued. Grout was placed. Quality assurance testing was performed.

Bulkhead installation continued at the 7th Street Turning Basin. Preparations were made for tieback installation.

Bulkhead installation began near 9th Street. Sheet pile installation continued.

Photos of construction activities are provided below.

Backfilling near the 4th Street Turning Basin.
Sheet pile installation near 9th Street.