Progress Update, Week of July 17th, 2023

During the week of July 17, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed south of Carroll Street.

Photos of construction activities are provided below.

Capping barge in transit to its next location for material placement.
GRT personnel sampling capping results.