During the week of July 1, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.

Supplemental dredging near Douglass Street continued. Sediment was removed.

Sunken barges were removed from the 6th Street Turning Basin (TB6) under archaeological supervision. More information about the barge removal is available on our Cultural Resources Page.

Probing activities were conducted near 6th Street and 9th Street.

Photos of construction activities are provided below.

Barge removal activities underway at TB6.
Probing near 9th Street.