During the week of July 27, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.
Bulkhead installation continued at the 6th Street Turning Basin. Tiebacks were installed.
Bulkhead installation continued at the 7th Street Turning Basin. Installed sheet piles were cut to final grade. Tiebacks were installed.
Photos of construction activities are provided below.