Skip to content

Progress Update, Week of July 27th, 2026

During the week of July 27, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.

Bulkhead installation continued at the 6th Street Turning Basin. Tiebacks were installed.

Bulkhead installation continued at the 7th Street Turning Basin. Installed sheet piles were cut to final grade. Tiebacks were installed.

Photos of construction activities are provided below.

Cutting sheet piles to final grade at the 7th Street Turning Basin.
Cutting sheet piles to final grade at the 7th Street Turning Basin.
Continued sheet pile cutting at the 7th Street Turning Basin.

Now Live: The Gowanus Transformation Through Generations Storymap