Progress Update, Week of July 28th, 2025

During the week of July 28, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.

Bulkhead installation continued near 9th Street. Grout was placed. Site restoration was performed at completed sections.

Bulkhead installation continued at the 7th Street Turning Basin. Tiebacks were installed. Grout was placed.

Bulkhead installation continued near Bush Street. Tiebacks were installed. Grout was placed.

Bulkhead installation continued at the 6th Street Turning Basin. Backfilling continued. Tiebacks were installed. Grout was placed. Piles were driven.

Photos of construction activities are provided below.

Tieback installation at the 6th Street Turning Basin.
Pile installation at the 6th Street Turning Basin.