Progress Update, Week of July 29th, 2024

During the week of July 29, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Gravel placement near Douglass Street continued.

The RTA 2 Bulkhead Installation Operation continued. Bulkhead/Structure Monitoring Equipment was installed. Access dredging was conducted near 3rd Street.

Divers were utilized to locate submarine cables at the Third street and Hamilton Ave bridges.

Photos of construction activities are provided below.

Access Dredging near 3rd Street.
Cable location underway near Hamilton Avenue.