Progress Update, Week of June 10th, 2024

During the week of June 10, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.

Supplemental dredging near Douglass St. continued. Sediment was removed.

Photos of construction activities are provided below.

Supplemental dredging in progress.
Continued supplemental dredging in progress.