Progress Update, Week of June 13th, 2022

During the week of June 13, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) near the Union Street Bridge. Daily closures were in effect during work between bridge abutments. Please visit https://gowanussuperfund.com/bridge-information/ for more information about extended bridge closures.

Monopile installation was completed at the Union Street Bridge and at the Carroll Street Bridge.

Photos of construction activities are provided below.

Installing southwest monopile at the Union Street Bridge.
ISS operations north of the Union Street Bridge.