During the week of June 15, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.
Bulkhead installation continued at the 6th Street Turning Basin. Installed sheet piles were cut to final grade. Drain outlets were installed.
Bulkhead installation continued at the 7th Street Turning Basin. Installed sheet piles were backfilled. Tiebacks were installed.
Bulkhead installation continued near Bond Street. Installed sheet piles were cut to final grade. Controlled low strength material was placed.
Photos of construction activities are provided below.