Progress Update, Week of June 23rd, 2025

During the week of June 23, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.

Bulkhead installation continued near 9th Street. Grout was placed. Site restoration was performed at completed sections.

Bulkhead installation continued at the 7th Street Turning Basin. Sheet piles were installed. Tiebacks were installed. Grout was placed.

Bulkhead installation continued near 3rd Street. Tiebacks were installed.

Bulkhead installation continued at the 6th Street Turning Basin. Sheet piles were installed. Sealant was placed.

Photos of construction activities are provided below.

Sheet pile installation at the 6th Street Turning Basin.
Tieback installation at the 7th Street Turning Basin.