During the week of June 24, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
Supplemental dredging near Douglass Street continued. Sediment was removed. Concrete and grout were placed.
Probing activities were conducted at bulkheads near 3rd Street.
Access dredging was conducted near the staging area.
Photos of construction activities are provided below.